Step-by-step installation guide for Cooper Stone limestone thin veneer. Written for working masons and general contractors — same approach applies to all our Traditional stones. For code-specific requirements, always follow your local jurisdiction and the Natural Stone Institute's thin veneer installation guide.
Over wood framing: install a weather-resistive barrier (two layers of 30-lb felt or equivalent code-compliant WRB). Lap and seal all penetrations. Install metal flashings at the base of the wall, over all openings, and at any horizontal change in plane. Leave a weep gap at the bottom of the installation.
Fasten 2.5 or 3.4 lb/yd² expanded metal lath through the WRB into the framing with galvanized or stainless fasteners (not into the sheathing alone). Lap all seams and orient the cups upward. Fasten every 6" vertically into studs and every 16" horizontally.
Trowel on a ⅜" to ½" scratch coat of Type N or Type S mortar over the lath. Fully embed the lath. While the coat is still plastic, score it horizontally with a notched trowel. Moist-cure for 24–48 hours before setting stone.
Dry-lay stones on the ground before setting to work out the pattern, color distribution, and size mix. For random ashlar, blend pallets to avoid color clumping. Set aside corner pieces for the outside corners — you'll alternate long-leg and short-leg across the courses.
Dampen the back of each stone with a wet brush. Apply a ½" to ¾" setting bed of mortar to the back of the stone, fully covering the surface. Press firmly against the scratch coat and wiggle slightly to squeeze out air pockets. Hold a few seconds. Work from the bottom up and from corners inward.
At every outside corner, set the corner pieces first. Alternate long-leg and short-leg orientation up the course. Fill flats in behind the corners once they're set. This alternation gives the completed wall the depth read of full-bed stone from every viewing angle.
Use a diamond-blade wet saw to cut stones for fit. Orient cut edges toward inside corners or where adjacent stones will cover them. Rinse cut dust from the face before pointing.
After the setting bed has set for several hours (but before 24 hours), fill the joints with mortar using a grout bag or pointing gun. Finish the joint per the design intent — flush, raked, or smear. For a smear joint (common on Hill Country residences), let mortar overflow slightly and soften with a damp brush.
Once the joints have firmed up (thumbprint hard), brush excess mortar off the faces with a soft masonry brush. Do not use acid on limestone — it will etch and discolor the stone face. If haze persists, use only a specialty limestone-safe cleaner per the manufacturer's instructions.
Protect the newly installed wall from rain and direct sun for 48–72 hours. Mist with clean water as needed to maintain moist curing. In hot or windy weather, cover with a tarp to slow evaporation and prevent premature drying cracks.